CF1R vs CF2R vs CF3R: Which Title 24 Form Is Which?

Residential Title 24 compliance uses three forms: the CF1R before the permit, the CF2R during construction and the CF3R after field verification.

Short answer: They are the three residential Title 24 forms, one for each stage of a project. The CF1R (Certificate of Compliance) shows the design meets the energy code before the permit. The CF2R (Certificate of Installation) is the installer's statement that what went in matches the CF1R. The CF3R (Certificate of Verification) is the ECC (HERS) rater's record of field tests. The building inspector expects the CF2R and, where the CF1R calls for verification, the CF3R before final.

Need a registered CF1R?

We prepare your Title 24 report and register it in CHEERS where the project requires it. ADU from $199 · Single-family from $245 · Multifamily from $345 per building. Delivered in 2–3 business days.

CF1R vs CF2R vs CF3R at a Glance

FormNameWho completes itWhenRegistered?
CF1RCertificate of ComplianceEnergy consultant (documentation author), signed by the responsible designerDesign stage, from the plans, before the permitYes, where the project requires registration
CF2RCertificate of InstallationInstalling contractorDuring construction, once the work is installedCompleted in the registry when the CF1R calls for ECC verification
CF3RCertificate of VerificationIndependent ECC (HERS) raterAfter installation, during field verificationYes, results are recorded in the registry

When the CF1R is registered, the installer's and rater's forms are tied back to it, so everyone on the job works from the same list of features. For how the registry works, see what CHEERS is.

CF1R: The Design-Stage Certificate

The CF1R is prepared from your plans, usually by modeling the design in CEC-approved software, and goes in with the permit application. It lists the insulation, windows, heating and cooling, water heating and other features the building must have, plus a summary of anything a rater will need to verify. There are several sub-types, such as CF1R-PRF-01 for the performance method, CF1R-ADD-01 for prescriptive additions and CF1R-ALT-02 for HVAC alterations; form names can change between code cycles. Our CF1R guide covers each section, and the CF1R sample report shows a real one.

CF2R: The Certificate of Installation

A CF2R is the installer's signed statement that the work was put in as the CF1R requires. The HVAC contractor completes one for a new system, and on larger jobs other trades may complete their own for the measures they installed. Under the 2025 code, heat pump installers also certify control settings on the CF2R, such as defrost timers and the lockout that keeps supplementary heat off in mild weather.

Because the CF2R records what was actually installed, it has to agree with the CF1R. Substituting equipment during construction can therefore mean the CF1R needs updating first; see when plans change.

Homeowner access to the CF2R

Homeowners can view their CF1R in CHEERS with no project access fee. Viewing the CF2R requires a one-time project access fee, charged per project rather than per document. The current amount is on our CHEERS fees page.

CF3R: The Certificate of Verification

The CF3R is completed by an ECC-Rater, still widely called a HERS rater, who visits the site, tests the items the CF1R flagged and registers the results. Typical items include duct leakage, refrigerant charge, airflow, fan efficacy, quality insulation installation and ventilation. The rater is independent of the installer, and a Consumer Information Form must be completed before verification starts. Not every project needs a CF3R, only those whose CF1R lists verification items. To check yours, see do I need a HERS rater; for what the rater does on site, see HERS rater vs Title 24 report.

How the Forms Line Up on Real Projects

A typical HVAC changeout

  1. A CF1R for the alteration is prepared, often a prescriptive HVAC alteration form, listing the verification items.
  2. The contractor registers the project and pulls the permit.
  3. The new system is installed, the contractor completes the CF2R and schedules the rater.
  4. The rater tests the system, completes the CF3R and the CHEERS Project Status Report.
  5. The building inspector signs off at final.

More on this project type: HVAC replacement Title 24.

A new single-family home

  1. A performance CF1R is modeled from the full plan set, registered and submitted for plan check.
  2. As each system goes in, its installer completes a CF2R: insulation, windows, heating and cooling, ventilation, water heating and, where required, solar.
  3. The rater visits at the stages the CF1R requires, since some items can only be seen before walls and ceilings are closed, and completes the CF3Rs.
  4. The inspector confirms the forms are complete before final.

See new construction Title 24 for the full process.

Nonresidential and Multifamily Equivalents

Commercial buildings use a parallel set of forms. NRCC forms are the certificates of compliance, split by system (envelope, mechanical, indoor and outdoor lighting, and others). NRCI forms are the installation certificates, and NRCA forms record acceptance testing. They are not CF1Rs, and some need a licensed professional's signature. For a commercial quote, use our commercial request form. Low-rise multifamily buildings use the LMCC for compliance; see CF1R vs LMCC.

Frequently Asked Questions

Is a CF2R the same as a permit card?

No. The permit card, or job card, is the building department's record of inspections. The CF2R is an energy code form the installer completes to certify the installation. The inspector may look at both at final.

Who signs the CF3R?

The ECC (HERS) rater who did the field verification, not the installer and not the energy consultant.

Can my HVAC contractor do the HERS testing?

No. The rater has to be independent of the installer. The contractor completes the CF2R and the rater completes the CF3R.

Does every project need all three forms?

No. A residential project that needs a Title 24 report starts with a compliance form, the CF1R for homes and ADUs. A CF3R is needed only when the CF1R lists verification items, and the building department decides what it needs to close the permit.

Does Title24Comply prepare the CF2R or CF3R?

No. We prepare and register the CF1R. The CF2R belongs to your installer and the CF3R to your rater. See pricing for the CF1R.

Questions & Answers

Related Title 24 Topics

Browse the complete Title 24 guide →

Why Choose Title24Comply?

  • CHEERS-Registered Reports
  • Fast 2–3 Day Turnaround
  • Rush Service Available
  • California Energy Specialists
  • Two Revisions Included
  • Permit Submission Ready
  • Affordable Fixed-Rate Pricing Starting at $199
  • 100% Online — Order From Anywhere in CA
HOW IT WORKS

From Order to Delivery

Simple, fast, and permit-ready.

Select your Title 24 report type, fill in project details, and pay online
1 Place Your Order

Select your report type, fill in your project details, upload your plans, and complete payment. The whole process takes under 5 minutes.

• Select Your Report Type • Fill In Project Details • Secure Online Payment
Our team reviews your architectural plans and prepares your Title 24 compliance report
2 We Prepare Your Report

Our team reviews your architectural plans, runs the Title 24 energy calculations, and gets your CF1R or LMCC report ready for submission.

• Plan Review & Analysis • CEC-Approved Software • CHEERS Database Filing
Title 24 report delivered to your email inbox as a permit-ready PDF
3 Delivered to Your Email

Your completed, permit-ready report is emailed to you as a PDF — stamped, CHEERS-registered, and ready to submit to your building department. Revisions are available if needed.

• Permit-Ready PDF by Email • Standard 2–3 Business Days • Two Revisions Included

Rush and same-day service are available. For urgent projects requiring delivery within a few hours, please contact us directly.

Ready to Order Your Title 24 Report?

Upload your plans, check out online, and get your permit-ready report in 2–3 business days. Starting at $199.

Contact Us