Home ADU Reports Residential Reports Multifamily Reports Commercial Reports Wholesale for Firms Title 24 Guide Pricing How It Works Services Locations Climate Zones About Contact Order Now →
Code Requirements

Title 24 Insulation Requirements by Climate Zone

Prescriptive attic, wall and floor insulation values for all 16 California climate zones under the 2025 code, and how the performance method changes them.

Short answer: Title 24 insulation requirements have two layers. Mandatory minimums apply in every climate zone: framed walls need at least R-15 in 2×4 framing or R-21 in 2×6 framing. Prescriptive values then vary by zone. Under the 2025 code, a vented attic calls for R-38 in Climate Zones 1 and 8–16 and R-30 in Zones 2–7, and raised floors call for R-19 everywhere. Most new homes and ADUs use the performance method instead, so your Title 24 report confirms the values your project must meet.

Need a Title 24 report for your permit?

ADU from $199 · Single-family from $245 · Multifamily from $345 per building. Permit-ready PDF in 2–3 business days, CHEERS-registered where required, two revisions included.

How Title 24 Insulation Requirements Work

The Energy Code treats insulation in three ways, and all three show up on a typical report:

For how insulation fits with windows, HVAC and the rest of the building, see Title 24 requirements. For how modeling trades features off, see Title 24 calculations.

Insulation Requirements by Climate Zone (2025 Prescriptive Values)

These values come from Table 150.1-A of the 2025 Standards for single-family buildings, as published on Energy Code Ace. They are prescriptive: the levels a design must meet if it does not use the performance method. The full table includes conditions and other components not shown here.

Climate zoneVented attic ceiling (Option C)Below-deck insulation (Option B)Framed wall, max U-factor
1R-38None listedU-0.048
2R-30None listedU-0.048
3R-30None listedU-0.048
4R-30R-19U-0.048
5R-30None listedU-0.048
6R-30None listedU-0.065
7R-30None listedU-0.065
8R-38R-19U-0.048
9R-38R-19U-0.048
10R-38R-19U-0.048
11R-38R-19U-0.048
12R-38R-19U-0.048
13R-38R-19U-0.048
14R-38R-19U-0.048
15R-38R-19U-0.048
16R-38R-19U-0.048

Two items are the same in every zone: raised floors at U-0.037 (R-19), and Quality Insulation Installation. Option C insulates the ceiling of a vented attic; Option B adds insulation below the roof deck. Which option suits a home depends on its roof and attic design, and your report shows the one modeled. Several of these values changed in this cycle; see 2025 Title 24 changes.

Mandatory Wall Insulation Minimums

Under §150.0(c), framed walls must meet a maximum U-factor of 0.095 for 2×4 framing (at least R-15 at 16 inches on center) or 0.069 for 2×6 framing (at least R-21). A lower U-factor means less heat flow, so it is the stricter number. The prescriptive wall value in the table, U-0.048 in most zones and U-0.065 in Zones 6 and 7, is lower than either mandatory limit. A wall built only to the mandatory minimum therefore does not meet the prescriptive value on its own. Under the performance method, a wall between the two can still work if other features compensate.

Attics, Cathedral Ceilings and Ducts

The 2025 code sets the prescriptive vented-attic ceiling value at R-38 in Climate Zones 1 and 8–16 and R-30 in Zones 2–7 (§150.1(c)1Aiii). Cathedral ceilings, where the ceiling follows the roof line, call for R-38 with no radiant barrier in all zones. Ducts in unvented attics may be insulated to R-4.2 when other requirements are met (§150.0(m)1Bi).

Ceiling insulation also matters on a re-roof. Where a steep-slope re-roof needs a cool roof, at least R-38 ceiling insulation is one of the accepted alternatives; see Title 24 re-roof requirements.

Quality Insulation Installation (QII)

Table 150.1-A lists QII as a prescriptive requirement in every climate zone. QII is field-verified: an ECC-Rater, still often called a HERS rater, checks the insulation and air sealing while they are visible, before walls and ceilings are closed. Plan the inspection into the construction schedule, because work covered too early may have to be opened up. Your CF1R shows whether QII applies to your design; see when a rater is needed.

Prescriptive or Performance: Which Values Apply to You

Most new homes and ADUs comply through the performance method, so the values on your report may differ from the table. A little more attic insulation can offset a wall, or better windows can offset a ceiling. Additions and alterations are handled differently: an addition can be modeled on its own or with the existing home, and altered components follow their own rules. Your report lists the insulation levels your plans must show.

How to Find Your Zone's Insulation Values

Your climate zone is set by the project address, not the city name alone. Look it up on our California climate zones page, then open the guide for your zone, for example Climate Zone 3, Climate Zone 9, Climate Zone 12 or Climate Zone 16. When you order a report, we confirm the zone from the address on your plans.

Frequently Asked Questions

What R-value do I need in my attic in California?

Under the 2025 prescriptive values, a vented attic needs R-38 in Climate Zones 1 and 8–16 and R-30 in Zones 2–7. A performance design may use a different value, and your report states the one that applies.

Do I have to upgrade insulation in my existing home?

Not because the code changed. Insulation requirements apply to new construction, additions and the parts of a home you alter. Some alterations, such as certain re-roofs, bring in insulation-related options, and your building department decides what the permit covers.

Can I use less insulation than the table shows?

Yes, under the performance method, if other features make up the difference and the mandatory minimums are still met. Under the prescriptive method, each value must be met as listed.

Is QII the same as the building inspection?

No. The building inspector checks the work against the approved plans. QII is a separate field verification by an independent ECC-Rater, and the results are registered with the data registry.

Questions & Answers

Related Title 24 Topics

Browse the complete Title 24 guide →

Why Choose Title24Comply?

  • CHEERS-Registered Reports
  • Fast 2–3 Day Turnaround
  • Rush Service Available
  • California Energy Specialists
  • Two Revisions Included
  • Permit Submission Ready
  • Affordable Fixed-Rate Pricing Starting at $199
  • 100% Online — Order From Anywhere in CA
HOW IT WORKS

From Order to Delivery

Simple, fast, and permit-ready.

Select your Title 24 report type, fill in project details, and pay online
1 Place Your Order

Select your report type, fill in your project details, upload your plans, and complete payment. The whole process takes under 5 minutes.

• Select Your Report Type • Fill In Project Details • Secure Online Payment
Our team reviews your architectural plans and prepares your Title 24 compliance report
2 We Prepare Your Report

Our team reviews your architectural plans, runs the Title 24 energy calculations, and gets your CF1R or LMCC report ready for submission.

• Plan Review & Analysis • CEC-Approved Software • CHEERS Database Filing
Title 24 report delivered to your email inbox as a permit-ready PDF
3 Delivered to Your Email

Your completed, permit-ready report is emailed to you as a PDF — stamped, CHEERS-registered, and ready to submit to your building department. Revisions are available if needed.

• Permit-Ready PDF by Email • Standard 2–3 Business Days • Two Revisions Included

Rush and same-day service are available. For urgent projects requiring delivery within a few hours, please contact us directly.

Ready to Order Your Title 24 Report?

Upload your plans, check out online, and get your permit-ready report in 2–3 business days. Starting at $199.

Contact Us